23 Avenue Interchange Project
Project Status PDF Print E-mail

2012 Landscaping

Landscaping for the remaining 23 Avenue Interchange project area will take place between mid-April and the end of June 2012. Landscaping activities include tree and shrub planting, top soil and seeding. The closure of the single outside lane can be expected for landscaping activities.

 

Construction Complete in mid-September 2011

Gateway Boulevard (northbound) at 23 Avenue was open to traffic on September 11, 2011 and Calgary Trail (southbound) at 23 Avenue was open to traffic on September 12, 2011. Construction was completed for the 23 Avenue Interchange project by September 22, 2011. Hard work from crews and continued patience from the public has resulted in completion of the interchange with minimal delays. Edmonton drivers, transit users and pedestrians will all benefit from this project which came in under budget and on schedule.

 

Introduction

The City of Edmonton has retained Team ISL, led by ISL Engineering and Land Services, to provide the engineering and related professional services for the preliminary design, detailed design and construction administration of the 23 Avenue/Gateway Boulevard Interchange project. The interchange configuration will be based on the recommendations presented in the icon Concept Plan (388.75 kB) that began in 2001. The final interchange configuration has  been modofied based on the recommendations presented in the icon Final Concept Plan (1.69 MB).

Please refer to the icon 2011 Construction Schedule (38.95 kB) and Shedule and Phasing page for the most current information regarding the project tender dates, schedule and phasing.